In July 2011, Power Engineering Consulting Joint Stock Company 3 (PECC3) signed with the Thermal Power 3 Project Management Unit the contract for construction, equipment installation supervision and consultancy, shop-drawing verification and approval and project management support services under the Duyen Hai 3 thermal power plant project with the contract value of VND 53,884,725,000.
SUMMARY OF PROJECT
Overview:
Duyen Hai 3 power plant project includes the installation of 2 coal fired condenser thermal power units; with the capacity of about 600MW each, configuration of 01 boiler + 01 turbine + 01 generator with necessary auxilary equipment systems and is connected to the national grid via the 500kV transmission line (The power center’s 220/ 500kV distribution yard which is invested by EVN NPT is not within the scope of the Duyen Hai 3 power plant project) and some shared items for Duyen Hai 3, Duyen Hai 2 projects and others.
The selected consultant will provide technical consultancy services for items: approving the shop-drawings; supervising the construction, installation and inspecting, accepting to put into operation of two units with auxiliary equipment and items as mentioned above.
The Unit 1 is expected to be put into commercial operation after 46 months and the Unit 02 and the whole plant are completed after 50 months from the effective date of the EPC Contract.
Location:
Duyen Hai 3 Power Plant belongs to Duyen Hai Power Center located at Mu U Hamlet, Dan Thanh Commune, Duyen Hai District, Tra Vinh Province and is about 45km to the southeast of Tra Vinh town;
Construction contract (EPC contract)
The Works include, but are not limited to, the following scope of works:
Construction: including foundation treatment, pile foundation work for the whole plant such as: chimney, main engine room, control building and other infrastructure and auxiliary works…etc.
Equipment: including the design, manufacture and procure, et, installation, testing and commissioning of equipment systems.
Project progress:
The project will be completed on time to meet load demand.
The expected milestones and progress are as follows:
Item
Completion time
(a) Commencement and handover of construction site
Quarter IV, 2015
(c) Completion of unit 01
Quarter IV, 2015
(d) Completion of unit 02 and the entire project
Quarter II, 2016
The contract completion period of this package is expected to be 74 months (of which 50 construction months and 24 warranty months under the EPC contract of Duyen Hai 3 power plant). However, the duties of Consultant will last until all claims/ issues are resolved and the Final Acceptance Certificate will be issued on the completion of the EPC contract.
The Consultant should review and submit monthly workday sheets and fair prices based on the above requirements.
Funds for consultancy services:
The funds for construction investment are raised by EVN:
Name of the project management agency:
The Thermal Power 3 Project Management Unit will act on behalf of the Investor – EVN to manage the Duyen Hai 3 Power Plant project.
Time, progress:
The contract completion period of this package is expected to be 74 months (of which50 construction months and 24 warranty months under the EPC contract of Duyen Hai 3 power plant). However, the duties of Consultant will last until all claims/ issues are resolved and the Final Acceptance Certificate will be issued on the completion of the EPC contract.
The Consultant should review and submit monthly workday sheets and fair prices based on the above requirements.