On September 21, 2019, in the Inauguration Ceremony of Vinh Tan 4 Thermal Power Plant Project (Vinh Tan 4 TPP), one of the national important projects on power network, Deputy Prime Minister – Mr. Truong Hoa Binh commended EVN and relevant authorities for 3 months earlier operation with safe and reliable quality and environmental protection regulations.
Deputy Prime Minister Truong Hoa Binh cuts the ribbon
At the ceremony, the Deputy Prime Minister asked EVN to promote applicating of science, technology and safe, reliable management and operation in order to contribute to ensuring the electricity supply for the country and no environmental pollution during the operation of the plant.
Deputy Prime Minister – Mr. Truong Hoa Binh speaks at the ceremony
The units get rewarded for a certificate of merit at the ceremony
Vinh Tan 4 TPP:
– The Ower: EVN
– Started: March, 2014
– Operation: March 31, 2018, 3 months earlier operation
– Output: 7.2 billion kWh/year
– Output up to now: 10.6 billion kWh
As the main consultant for the project owner on project management and construction supervision, with the professional, dynamic, creative team and dedicated construction engineers, EVNPECC3 contributed to the overall success of the project.