EC contract signing and beginning construction of hydropower project A Lin B1- Thua Thien Hue

August 30, 2010, Truong Phu Hydropower Corporation  held a groundbreaking ceremony Hydropower Project A Lin B1 – power rated capacity of 42 MW in Hong Trung commune, A Luoi District, Thua Thien Hue.

Hydropower project A Lin B1 is hydropower project path Alin B1 Hydro Power Plant was built in Hong Van commune, the Hong Trung A Luoi district and Xuan Phong commune, Phong Dien district, Thua Thien Hue province. This is industrial project level III. Reservoirs in the drainage basin on West of Truong Son and Lin A reservoir on the Lin A river on East of the Truong Son,  through two reservoirs  communicates by the A Lin B1 tunnel number 1 with 4372 m of length.

With power rated capacity of 3 units x 14 MW, and total investment of the project is 920 billion VND, when put into operation, annual hydropower A Lin B1 can provide average 177 million kWh to the national grid.

hp img 0001

Thua Thien Hue province’s leaders, investors and contractors started groundbreaking ceremony

At the groundbreaking ceremony, Mr. Thai Tuan Tai – Chairman – General Director of Power Engineering Consulting Joint Stock Company 3, representing to the consortium PECC3 – Long Thanh – Ha Dung committed to mobilizing resources management and coordination on implementation to complete on schedule, quality assurance according to specifications.

hp img 0002

The provincial leaders, investors and contractors taking picture at groundbreaking ceremony

Previously, 14 August, 2010, the contract signing ceremony on package 73 EC1 waterway, is the largest construction bid of the project was signed in Hue city betweenCorporation and Power Engineering Consulting Joint Stock Company 3- Investment in construction of Long Thanh Ha Dung Co., Ltd (Consortium PECC3-Long Thanh – Ha Dung) after the bidding process and contract negotiation.

Bid package 73 EC1 includes survey, construction design, drawings, supply of construction materials and complete the items of the end of the leading channel to  A Lin B1 with length 103.27m connected to tunnel A lin B1 number 1, length 4.372m; leading channel A Lin B1 length 815,7m; tunnel A Lin B1 number 2, length 1.262m; restoration road 71 and maintenance in 03 years for construction .

Package 73 EC1 waterway will be surveyed and designed, constructed and completed by consortium in 30 months from the effective date of the contract.

hp img 0003

Leader of  Investor and consortium signing contact

Tran Quoc Dien