25/03/2024
On 24th of March 2024, the EPC project "LEGO 110kV substation and connection” has been successfully energized and put into safe operation. The project is implemented by the Consortium of contractors of Power Engineering and Consulting Joint Stock Company 3 (“PECC3”) and Information Technology Application and Development Joint Stock Company ("PECC3-AIT Consortium") - in which PECC3 is the leading member; the investor is LEGO Manufacturing Vietnam Co., Ltd. ("LEGO Vietnam"). Photo 1. Fire truck on duty at the substation during the energization The project is located in the area of LEGO factory - 44ha - in Vietnam - Singapore Industrial Park III in Hoi Nghia ward, Tan Uyen city, Binh Duong province. Notable works include two 110/22kV transformers with a capacity of 40MVA each, a control house, a 110kV distribution yard system installed outdoors and a 22kV distribution system installed indoors. New construction of 110kV transmission lines connecting substations on…